MARATHON – Road work in Marathon is scheduled to begin on May 30 until June 27.
Taranis Contracting Group will do the less invasive work, including ditching, culvert flushing, concrete removal replacements, and culvert replacements.
The scope of work includes removing and replacing culverts, which impacts the need to remove existing channels, concrete sections, asphalt or interlocking driveways. All affected areas will be replaced or reinstated, and a couple of teams will have gutters removed and new ditches established.
One lane of traffic will be maintained for local traffic; however, please expect traffic delays during construction.
The roadway will still be open while progressing through the work to ensure school transportation is not disrupted. After June 27, Taranis will proceed into the more invasive aspects of the project, such as asphalt removal and paving.
Work is expected to be complete by Aug. 15.